February 2026

Project team remobilised and procurement of wider consultant team

March 2026

Design development begins

May 2026

Pre-application meetings with Planning and external funding partners

October 2026

Planning submission

December 2026

Contractor procurement

March 2027

Spring 2027: Contractor expected to be appointed

April 2027

Spring 2027: Start of on site construction

July 2027

Practical completion and operator fit out