Works to resurface junction in August
We’re resurfacing the junction of Forest Road, Wood Street and Fulbourne Road in late August.
Between the evening of Friday 21 August to the morning of Monday 24 August, teams will be on site between 8pm and 5am.
During these times:
- The junction will be completely closed to traffic, except for emergency services
- Some parking bays will be temporarily suspended
- Signed diversion routes will be in place for motorists
- Bus routes will be diverted – visit tfl.gov.uk/bus/status/ for more information.
We apologise for the inconvenience this will cause and will do our best to minimise disruption while these works are being carried out.
We’re also continuing to coordinate our programme with utility companies and Transport for London to help reduce pressure on the network where possible.
Following the completion of this phase, preparatory work will begin for the next stage of construction between Kinglsey Road and Melsetter Road in September.